Ground Improvement Work

HOME WHAT WE DO Ground Improvement Work

Our Services

for GROUND IMPROVEMENT

  • DCM (Deep Cement Mixing Method)
  • UCI (Underground Cutting Injection)
  • SCW (Soil Cement Wall)
  • Surface Treatment : Dynamic Replacement
  • Concrete Diaphragm Wall
  • Jet Grouting
  • JSP (Jumbo Special Pattern)
  • Surface Treatment : Dynamic Compaction
  • Surface Treatment : Rapid Impact Column

Innovative Technology

Sheet Piling : Temporary/Permanent for Various Application

Steel Sheet Pile Tubular Sheet Pile Concrete Sheet Pile Synthetic Sheet Pile
Material Steel Sheet Pile Steel Tubular Pile Reinforced Concrete Plastic or Glass Fiber Reinforced Plastic
Profile U, Z, I, H, Box, Combi. Tubular Section To Design, Normally U or Flat U, Z, I, Box Profile
Photo
Application Temporary Shoring
Permanent Quay Wall etc.
Temporary Shoring
Permanent Quay Wall etc.
Permanent Wall Structure Permanent Wall Structure
Cost High
(Recyclable)
High
(Recyclable)
Moderate (Low for Permanent Application) Low
(Limited Application)
Evaluation

Good Structural Performance

Easy Handling & Driving

Corrosion Issue

Excellent Structural Performance

Easy Handling & Driving

Corrosion Issue

Good Structural Performance

Need Care for Driving

Corrosion Free

Low Structural Performance (Flexible)

Need Care for Driving

Corrosion Free

Steel Sheet Pile Tubular Sheet Pile Concrete Sheet Pile Synthetic Sheet Pile
Material Steel Sheet Pile Steel Tubular Pile Reinforced Concrete Plastic or Glass Fiber Reinforced Plastic
Profile U, Z, I, H, Box, Combi. Tubular Section To Design, Normally U or Flat U, Z, I, Box Profile
Photo
Application Temporary Shoring
Permanent Quay Wall etc.
Temporary Shoring
Permanent Quay Wall etc.
Permanent Wall Structure Permanent Wall Structure
Cost High
(Recyclable)
High
(Recyclable)
Moderate (Low for Permanent Application) Low
(Limited Application)
Evaluation

Good Structural Performance

Easy Handling & Driving

Corrosion Issue

Excellent Structural Performance

Easy Handling & Driving

Corrosion Issue

Good Structural Performance

Need Care for Driving

Corrosion Free

Low Structural Performance (Flexible)

Need Care for Driving

Corrosion Free

Country Malaysia
Project TNB 3A 1000MW CFPP
Client TNB
Main Contractor DAELIM Industrial Co.
Case-1
Original Design Bored Pile (1000mm up to 60m depth)
Alternative Steel Tubular Pile Driving (1000mm up to 60m depth)
Outcome Shorten Schedule (4.5month)
Case-2
Original Design Sheet pile
Alternative Steel Tublar Pile Driving (1200mm) width LT Clutch for sheet pile
Outcome Shorten Schedule Improve safety & constructability

Controlled Modulus Column

Conventional Piling CMC Advantage
Require concrete pile cap Could be granular mattress (w/geogrid)

Cost saving by eliminating “pile cap concrete, piling work”

Mostly effective for large diameter tank farm

Pile : Reinforced Concrete Pile : Plain Cement Pile
Deeper depth to get bearing capacity Terminate at shallower depth, subject to settlement evaluation
Conventional Piling CMC Advantage
Require concrete pile cap Could be granular mattress (w/geogrid)

Cost saving by eliminating “pile cap concrete, piling work”

Mostly effective for large diameter tank farm

Pile : Reinforced Concrete Pile : Plain Cement Pile
Deeper depth to get bearing capacity Terminate at shallower depth, subject to settlement evaluation

Deep Cement Mixing Method

Application

Reinforcing Slope Stability

Increase Bearing Capacity

Ground Stabilization

Stabilizing for Deep Excavation

Jet Grouting

Application

Reinforcing Slope Stability

Increase Bearing Capacity

Ground Stabilization

Stabilizing for Deep Excavation

Dynamic Compaction / Replacement

Application

Fine ~ Coarse Grain

Improvement depth to ~ 10m

Increase up to SPT N≈20

Effective for large area for shallow treatment

Rapid Impact Column

Application

Fine ~ Coarse Grain

Improvement depth to ~5m

Increase up to SPT N≈20

Effective for large area for shallow treatment

Concrete Diaphragm Wall

Application

Temporary (or Permanent) Wall for Deep Excavation / Underground Structure

Permanent Wall (Channel, Quay Wall etc.)

Barrette Pile for Heavily Loaded Structure

Cost effective solution when utilizing as permanent structural part

Save internal working space by eliminating internal support system with circular shape, especially for sea water intake pumping station work.